756,000 SF. From design kickoff to a fully enclosed elevated deck in less than eight months. Here’s how the schedule came together: • Design kickoff: January 6, 2026 • Manufacturing began: February 23, 2026 • Erection began: May 19, 2026 • Erection complete and building enclosed: August 26, 2026 That’s Agile Delivery with Clark Pacific’s AccelCore™ system. AccelCore™ is designed to create flexibility earlier in the process, allowing manufacturing to begin without waiting for extensive design coordination to be completed. The result is a prefabricated approach built to support speed, reduce schedule risk and provide greater certainty on complex data center projects. What does your data center prefabrication and delivery strategy look like? #AccelCore #DataCenters #Prefabrication #Hyperscale
Construction at our Pecos, Texas site is moving full speed ahead, and we remain on track for delivery of the first tranche in early 2027. Five months ago, this campus was dirt. Today, we're installing the first data hall's chillers. This is what execution looks like. As we continue to scale, Pecos is a clear signal of our commitment to delivery and expansion.